ADU Site Prep & Utilities in Ojus: Timeline, Scope, and Real Costs
ADU site prep and utilities in Ojus typically runs $45,000 – $130,000 for the preparation phase of a detached or attached unit, and the buildable scope depends on how much of the lot’s existing infrastructure survives. The prep stage itself – clearing, grading, utility trenching, and the concrete foundation flatwork – usually takes four to eight weeks from permit pull to the first wall going up. Call (833) 716-6251 for a free on-site estimate before you commit to anything; live person answers, 24/7.
How We Handle Site Prep and Utilities, Step by Step

Site prep for an ADU isn’t a quick clearing-and-grading job. It’s the infrastructure phase that has to be right before anything structural goes in. Here’s how the sequence actually plays out.
Stage 1: Site survey and utility locate (days 1 – 3)
We walk the lot, locate existing electrical service, water mains, and sewer lateral connections, and call for the utility locates. On Ojus lots in 33179, older single-family parcels often have undersized or failing laterals, so this walk frequently turns up surprises. You’ll need to decide whether the ADU ties into the existing lateral or runs a new one – that’s a permit-scope call, and it bumps the budget.
Stage 2: Demolition and clearing (week 1)
Anything on the build pad comes out – old fence lines, concrete flatwork, landscaping, a shed, or a pool deck. On teardown-to-infill lots along the 33179 corridor, this stage can surface undocumented footings or old septic remnants. We haul it and grade the pad level. You decide how much of the existing yard footprint comes out versus stays.
Stage 3: Grading, drainage, and forming (week 2)
Final grade, stormwater drainage, and the foundation formwork go in. Ojus sits on the flat coastal plain south of the Broward line, so drainage has to be engineered for summer downpours – grading falls away from the pad and connects to existing swales or dry wells. The pad is compacted and inspected before concrete pours.
Stage 4: Concrete flatwork and foundation pour (week 3 – 4)
Footings, slab, and utility sleeves go in. The slab has to accommodate your utility penetration points, and once the pour is done, that layout is locked. You decide the slab size and the number of utility penetrations before the pour – not after.
Stage 5: Utility rough-in and inspection (week 5 – 8)
Electrical conduit, water supply, and sewer stub-outs run from the main service to the ADU pad. All rough-in gets inspected and approved before backfill. Once the rough-in signs off, the site is ready for the ADU structure phase – the framing, roofing, and finishes work covered in our Home Additions & ADU in Ojus page.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Choices You’ll Make Before the Concrete Pours
The site prep and utility work locks in decisions that are expensive to change later. Here’s what you’re actually choosing between, and what each choice costs you in money or flexibility.
- Slab-on-grade vs. raised/engineered foundation: Slab-on-grade is the standard for Ojus ADUs – it’s the lower-cost option and works with the existing grade. A raised or engineered foundation costs more but suits lots with poor drainage or where the ADU footprint sits near a swale edge.
- Tie into existing utilities vs. new service: Tying into the existing electrical panel and water main is cheaper but only works if the panel has spare capacity and the lateral is in good shape. New service runs cost more and take longer to permit, but avoid fighting with an undersized 1970s panel.
- Conduit sizing for future capacity: Running a 1″ conduit vs. a 1.5″ or 2″ conduit is a small cost difference now, but a bigger one in a decade if you want to add a subpanel or a second unit later. We’ll tell you what makes sense for the lot.
- Drainage approach: A simple graded swale costs less than a reinforced concrete dry well or a French drain system. On flat Ojus lots, we usually recommend the larger capacity approach – summer rain season doesn’t give you a second chance to redo the drainage.
- Pad size and utility penetration points: How many penetrations, where they sit, and the slab footprint all lock in at this stage. Decide before the pour, or you’re paying to cut later.
What ADU Site Prep & Utilities Costs in Ojus, FL

Site prep and utilities in Ojus run $45,000 – $130,000 for the prep phase alone. The full ADU project – structure, finishes, systems – sits in the $90,000 – $220,000 range. This page focuses on the prep and utility scope.
The number you get depends on five variables:
- Lot size and clearing scope: A lot with nothing to remove sits at the low end. A lot with old concrete, trees, or a teardown remnant pushes toward the high end.
- Utility tie-in complexity: Tying into existing infrastructure keeps costs down. Running a new sewer lateral or upgrading the electrical service is where the price moves most.
- Foundation design: Standard slab-on-grade foundations sit at the low end. Engineered or raised foundation work adds cost.
- Drainage engineering: A simple graded swale vs. an engineered dry well system or French drain is a clear cost split.
- Permit scope: A Miami-Dade County permit with a straightforward utility rough-in is less expensive than a scope that touches multiple jurisdictions or triggers additional inspections.
Every written estimate is line-item and fixed – upfront pricing, no surprises. We don’t quote a ballpark and then chase change orders once the concrete is on the ground. Call (833) 716-6251 to schedule the free on-site estimate.
See the difference
Before
After
Before
After
Before
AfterWhat Ojus Homes Specifically Do to This Job
Ojus sits at the northern edge of Miami-Dade, wedged between incorporated cities, and the 33179 stretch is unincorporated county land. That matters before you break ground: we pull Miami-Dade County permits for the site prep and utility rough-in, but a job on the far side of the Broward line jumps to a separate jurisdiction and inspection regime. The whole permitting sequence gets coordinated across Miami-Dade and Broward lines. That’s a different reality from a greenfield build.
The housing stock makes it worse. Most of the parcels here are post-war ranch homes and 1960s – 70s apartment/condo blocks with CBS walls, flat or shallow-pitch roofs, and original single-pane openings. That means when we open the ground for a utility tie-in, we’re often working around undersized 1970s laterals and electrical panels already at capacity. Hurricane-season wind exposure adds another layer: even the site prep has to account for the High-Velocity Hurricane Zone product approvals the ADU itself will need, so conduit layout and foundation terms get planned with AAF-rated doors and impact glazing on the ADU down the line – part of the same build. If the yard is being torn up, homeowners often pair this with Concrete Driveways & Concrete Work in Ojus or Paver Driveways in Ojus to rebuild the rear access before the ADU goes up.
Serving Ojus, FL – Our Local Coverage Area
We serve Ojus and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked – ADU Site Prep & Utilities in Ojus

Four to eight weeks from permit pull to completed utility rough-in, with the concrete flatwork usually done by week four. The timeline stretches on lots with old lateral issues or where a Miami-Dade permit triggers additional utility locate reviews. Call (833) 716-6251 for a permit-timeline estimate – the free on-site visit covers it.
Yes. Site clearing, foundation work, and utility rough-in all require permits in Ojus, and the permit path depends on whether the lot sits in unincorporated Miami-Dade County or crosses the Broward line. The 33179 corridor pulls Miami-Dade permits; jobs just north across the county line trigger a separate Broward inspection regime. We handle the permit pull and coordinate every inspection for you – call (833) 716-6251 to get the scope reviewed.
Only on lots where the existing panel and utility laterals already have spare capacity and the grading works without drainage changes. On most Ojus lots built in the post-war era, the existing 1970s-era service pulls the prep scope into utility upgrades. We assess that in the first three days, and the estimate tells you which path your lot is on – call (833) 716-6251 for that estimate.
$45,000 – $130,000 for the prep phase. The low end covers a clean lot with existing utility tie-ins and standard slab work; the high end covers a teardown-to-infill lot with new lateral runs, drainage engineering, and a broader Miami-Dade permit scope. Call (833) 716-6251 for an exact quote – estimates are free and line-itemed.
The 730-Day Done Right Promise covers every stage of the job – if it’s not done right, we make it right. That’s two full years on the concrete flatwork, the utility rough-in, and the drainage. To get the first stage scheduled, call (833) 716-6251 for the free estimate and on-site walkthrough.
Homeowners who aren’t sure about the larger build sequence should start with our Home Additions & ADU service overview. We cover Ojus and the surrounding areas served through our Ojus service area page – all jobs pull the right permits and pass inspection.
Get Your Free ADU Site Prep Estimate in Ojus
Call (833) 716-6251 to schedule your free on-site estimate for ADU Site Prep & Utilities in Ojus. We’ll walk the lot, locate the existing utilities, and give you a line-itemed written estimate the same visit – no ballpark guesses, no pressure. The 730-Day Done Right Promise backs every job, and 0% financing for 18 months is available. Call today; live person answers around the clock.