New Detached ADU in Ojus: What It Costs and What’s Realistic
A new detached ADU in Ojus runs $90,000 – $220,000 from design through final inspection, with the general Home Addition range starting at $45,000 – $130,000 for smaller attached scopes. A full detached unit, meaning its own foundation, roof, utilities, kitchen, and bath, typically takes 6 to 10 months of construction once permits clear Miami-Dade County. Call (833) 716-6251 for a free on-site estimate before you commit to a number.
How We Build a Detached ADU in Ojus, From Day 1 to Final Inspection

The sequence below is what actually happens on a Ojus detached ADU job. Not a marketing summary. Every stage has a decision point, and delaying that decision extends the schedule.
Stage 1: Site Assessment and Feasibility (Week 1 – 2)
We start by walking the lot and measuring setbacks. In unincorporated Miami-Dade, the buildable envelope on a 1950s – 70s lot is often tighter than the homeowner expects because of side-yard setbacks and drainage requirements. By the end of week two you’ll know whether your lot supports a detached unit or whether a different configuration is the honest answer. This is where the footprint size gets locked.
Stage 2: Design and Permit Submission (Weeks 3 – 12)
Site plan, floor plan, structural drawings, and product approvals get submitted to Miami-Dade County. Approval timelines on ADUs have stretched as the county works through redevelopment volume in this corridor, so plan on 8 to 14 weeks of permit review, not a few days. You’ll decide the roof profile, wall assembly, and glazing here because those approvals go in with the package.
Stage 3: Site Prep and Foundation (Weeks 1 – 4 After Permit)
Utility locating comes first, then grading, then a monolithic slab or stem-wall foundation depending on the soil and design. Ojus sits on flat ground with a high water table during wet season, so we build in drainage swales and finish floor heights that keep the unit above standing water. Storms in June through September will pause concrete work; we schedule around that reality rather than pretending it away.
Stage 4: Structure, Envelope, and Rough-In (Weeks 5 – 16)
CBS block and stucco is the standard wall here, matched to the existing house. Roof framing, sheathing, and Miami-Dade approved impact glazing go in next, then plumbing, electrical, and HVAC rough-in. The county inspects rough-in before walls close. This is the stage where a change to the unit’s layout costs the most, so lock the interior before framing starts.
Stage 5: Finishes, Punch List, and Final Inspection (Weeks 17 – 28)
Drywall, cabinets, counters, flooring, plumbing trim, and electrical trim complete the unit. We walk a written punch list with you, then the county performs final inspection. Utility tie-in to the main house or separate meters gets confirmed here. Only after that do we hand over keys.
This whole sequence is a full project, and some homeowners expand it into a broader scope by pairing the ADU with a main-house upgrade. If that’s your plan, our Home Additions & ADU in Ojus page covers the wider work, while this page stays on the detached unit itself.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Options You’ll Choose Between Before Framing Starts
Most of the money on a detached ADU is spent in decisions, not labor. These are the real trade-offs.
- Footprint size: a compact 500 – 700 sq ft studio runs toward the low end; a 900 – 1,200 sq ft two-bedroom pushes toward the high end. Every 100 sq ft adds roughly $12,000 – $18,000 depending on fixtures.
- Wall assembly: CBS block and stucco matches the Ojus housing stock, holds up to sun and wind, and is the default for permitted detached units. Wood-frame construction is faster but needs more ongoing maintenance in South Florida humidity.
- Roof: a low-slope membrane roof works well with the flat and shallow-pitch rooflines common on this corridor, while a shingle roof is affordable but shorter-lived in the heat. A standing-seam metal roof costs more upfront and lasts longer. We work with GAF on shingle systems where the design calls for them.
- Glazing: impact-rated windows and doors are effectively required in the High-Velocity Hurricane Zone. Skipping that approval isn’t an option on a permitted build.
- Kitchen and bath finishes: builder-grade quartz and slab-front cabinets land near the low end; custom cabinetry and stone counters push toward the high end. Our cabinet partners include KraftMaid for the semi-custom tier.
- Metres and utilities: tying into the main house service is cheaper; separate electrical service and a standalone water meter cost more and take longer at the permitting stage.
What a New Detached ADU Costs in Ojus, FL

Expect $90,000 – $220,000 for a detached ADU in Ojus, depending on size, finishes, and utility configuration. A studio with builder-grade finishes sits near $90,000 – $130,000; a two-bedroom with custom cabinetry, stone counters, and separate meters lands in the $170,000 – $220,000 range.
Five variables push that number:
- Square footage: the largest single driver, and it also affects permit fees.
- Site conditions: tight lots, older utility laterals, and drainage work add cost.
- Utility separation: separate meters and a second electrical service add real dollars.
- Material grade: cabinets, counters, flooring, and fixtures swing the finish budget by $20,000+.
- Permit scope: a detached unit requires its own full permit package, separate from any work on the main house.
Your written estimate itemizes each line: foundation, framing, envelope, rough-in trades, finishes, permits, and inspection fees. It does not include landscaping, pool work, or optional hardscape. If you’re grading the lot anyway, homeowners often pair this with Paver Driveways in Ojus or with Concrete Driveways & Concrete Work in Ojus to finish the yard in one pass. Upfront pricing means the number you see is the number you pay on the scope we agreed.
See the difference
Before
After
Before
After
Before
AfterWhat Ojus Homes Specifically Do to This Job
Ojus sits at the northern edge of Miami-Dade, right where the county line meets Broward and the I-95 corridor. Most of the housing stock in 33179 is unincorporated-area 1950s – 70s single-family homes and low-rise multifamily, and a large share of it is being redeveloped into mid-rises and townhomes. That means the work here is dominated by teardown-to-infill on older lots, not greenfield construction. Existing lots were platted decades ago, so setbacks, drainage, and utility easements keep the buildable envelope tight. And because this stretch of land is unincorporated, we routinely pull Miami-Dade County permits while a job on the far side of the Broward line jumps to a completely different jurisdiction with its own inspection regime. The other constant: High-Velocity Hurricane Zone requirements apply to every ADU built here, so impact glazing and wind-rated connections aren’t optional upgrades.
You can see the wider pattern on our Ojus service-area page, but the short version is that a detached ADU here is a permitting and drainage exercise as much as a construction project.
Serving Ojus, FL – Our Local Coverage Area
We serve Ojus and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked Questions About New Detached ADU in Ojus

Plan on 6 to 10 months of construction after permits clear, plus 8 to 14 weeks of permit review. The single biggest accelerator is locking design decisions before the permit package goes in.
Yes. A detached ADU requires its own building permit through Miami-Dade County, with separate inspection sign-offs at foundation, rough-in, and final. We pull the permits and schedule inspections. You don’t handle paperwork.
Yes. A detached unit runs its own plumbing and electrical service, so no wall in the main house has to open unless you choose to tie in. Separate meters cost more but avoid any disruption to the main house.
The range is $90,000 – $220,000 depending on size, finishes, and utility configuration. Written line-item quotes with fixed pricing mean the number you see is the number you pay on the agreed scope. Call (833) 716-6251 for an exact free estimate.
Every ADU project is covered by our 730-Day Done Right Promise. If something isn’t done right, we make it right. The technicians on the job are background-checked and arrive in uniform.
Get a Free Estimate on Your New Detached ADU in Ojus
If you’re weighing a New Detached ADU in Ojus, the next step is a free on-site estimate. Call (833) 716-6251. We answer live, 24 hours a day. On the visit, we measure the lot, check setbacks against Miami-Dade County rules, and walk you through a written line-item price with fixtures and finish options spelled out. Bring questions about timeline, utilities, or financing: 0% financing for 18 months is available, plus $1,000 off projects over $10,000.