Free written scope consultation - allowances, timeline, and change-order rules on paper before a single trade is scheduled
Garage Conversion ADU in Sunny Isles Beach, FL: What It Actually Takes
A Garage Conversion ADU in Sunny Isles Beach runs $45,000 – $130,000 and takes roughly 4 to 7 months from permit to final inspection. You’re turning an existing garage into a legal, permitted living unit, which means new electrical, plumbing, insulation, impact-rated openings, and a separate entrance. Call (833) 716-6251 and we’ll walk your garage and give you a real number, not a ballpark over the phone.
How the job unfolds, stage by stage
Every conversion we do in Sunny Isles Beach follows the same sequence. The durations below are what we typically see on the island; larger garages or complicated utility relocations stretch them.
- Stage 1 – Site assessment and design (1 – 2 weeks). We measure the slab, check ceiling height, map where the water heater, AC air handler, and electrical panel sit, and confirm what the garage is actually framed with. You decide the layout at this stage: studio versus one-bedroom, where the bathroom goes, whether the laundry stays. The big decision here is whether the water heater and air handler move or stay behind a service closet. Moving them frees up floor space but adds cost.
- Stage 2 – Permits and plans (4 – 8 weeks). We submit stamped drawings to the city. This is the longest waiting period in the whole job, and it’s also where most of the inspection scoping gets locked in. You sign off on the final plan set before anything gets demoed.
- Stage 3 – Demo and rough-in (2 – 3 weeks). Out comes the old garage door, any shelving, and the existing slab finish. In goes the new plumbing rough and electrical rough, plus framing for the bathroom and closet walls. Rough inspections happen at the end of this stage. This is where you confirm fixture locations on the wall.
- Stage 4 – Insulation, drywall, and systems (3 – 5 weeks). We close the walls, install the mini-split or tie into the existing HVAC, set the water heater if it moved, and hang and finish drywall. You’ll pick finishes before this stage starts: flooring, tile, paint, door style. Slip-ups happen here when a homeowner changes their mind late.
- Stage 5 – Finishes and final inspection (3 – 4 weeks). Cabinets, countertops, fixtures, paint, trim, and the new impact-rated entry door and windows. Final inspections run, then we do a walkthrough with you. You get the certificate of occupancy before you move anyone in.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The choices that decide what your conversion looks like
The specs you pick drive both the price and how the unit holds up in a salt-air climate. Here’s what you’re actually choosing between:
- HVAC: mini-split vs. tying into the house system. A ductless mini-split runs a few thousand dollars and keeps the ADU on its own thermostat, which suits a rental or an in-law suite. Tying into the existing system is cheaper upfront only if the panel has capacity and the run is short; a twelve-year-old air handler that has to serve an extra 400 square feet often needs upsizing, which eats the savings.
- Impact-rated door and windows. In Sunny Isles Beach, the new entry door and any windows must meet Florida wind-load and impact-glazing rules. Standard units won’t pass. This is a fixed cost, not a style choice, and it’s one of the first things an inspector checks.
- Flooring: luxury vinyl plank vs. porcelain tile. LVP is warmer underfoot, faster to install, and forgiving on a slab that isn’t perfectly level. Porcelain tile handles moisture and looks sharper with a floor drain, but it’s a slower, pricier install. For a ground-level garage conversion in a humid climate, we lean toward tile in the bathroom and LVP everywhere else.
- Moisture barrier under the slab. Garages were never built to keep moisture out. A vapor barrier and a new slab topping add cost but prevent the musty smell that ruins rentals this close to the ocean. Skipping it is the single most common shortcut we correct.
- Fixtures and finishes. We use Sterling and Grohe plumbing fixtures on these builds. They cost more than builder-grade and last longer behind a wall you won’t want to open again. You can go cheaper here; the trade-off is replacing a leaking valve in five years.
- Separate entrance and privacy. A detached entry door on the side of the garage suits a renter; a shared hallway suits family. The layout is locked at permit time, so this is a stage one decision.
What a Garage Conversion ADU costs in Sunny Isles Beach, FL

Expect $45,000 – $130,000. The broad range reflects how differently two garages of the same size can be built out. Single-car conversions generally land in the bottom half; two-car garages with a full bathroom, kitchenette, and a relocated water heater land near the top. As part of a Home Additions & ADU in Sunny Isles Beach project, this is often the least expensive way to add square footage, because the shell already exists.
The variables that move the number:
- Existing garage condition. A cracked, settling slab or a wall full of termite damage resets the baseline upward before finishes even come up.
- Utility relocation. Moving the electrical panel, water heater, or AC air handler out of the footprint is real work with real cost.
- Bathroom and kitchenette scope. A powder room is much cheaper than a full bath with a shower; a kitchenette with a cooktop and sink is cheaper than a full kitchen.
- Impact glazing and entry requirements. Mandatory in this coastal zone, and non-negotiable on the plan set.
- Finish grade. The gap between builder-grade and a Sterling-and-Grohe build-out shows up here.
- Permit scope and inspection count. A straightforward studio is cheaper than a multi-room unit that triggers more inspection stages.
A written line-item estimate from us lists permits, demolition, rough-ins, insulation, drywall, finishes, impact door and windows, and the final walkthrough as separate lines. It doesn’t cover landscaping restoration you ask for separately, or furniture. The number in that estimate is the number you pay, covered by our 730-Day Done Right Promise and paired with 0% financing for 18 months plus $1,000 off projects over $10,000.
See the difference
Before
After
Before
After
Before
AfterWhat Sunny Isles Beach does to this job specifically
Most of our work in Sunny Isles Beach is in 33160, and the housing stock shapes the job. This is a barrier-island city of high-rise condos and hotels stacked along Collins Avenue, with a shrinking pocket of mid-century single-family homes and small motels on the west side toward the Intracoastal. Those west-side homes are the ones with garages to convert, and they were largely built in the 1950s through the 1970s, so the slabs are original, the electrical panels are older than they look, and the framing was never designed for a conditioned living space. The salt-laden Atlantic air attacks the envelope first: hardware, fasteners, and any exposed metal on the garage door or window frames corrode years faster here than inland, which is one reason we specify galvanized and stainless hardware and insist on a proper vapor barrier. Hurricane wind-load and impact-glazing rules apply to every opening. If you’re already replacing the drive while you’re at it, homeowners often pair this with Concrete Driveways & Concrete Work in Sunny Isles Beach, since the garage door comes out anyway.
Serving Sunny Isles Beach, FL – Our Local Coverage Area
We serve Sunny Isles Beach and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently asked – Garage Conversion ADU in Sunny Isles Beach

Plan on 4 to 7 months: roughly 4 to 8 weeks for permits and plans, then 8 to 12 weeks of construction. The permit wait is the biggest variable. Call (833) 716-6251 for a timeline specific to your garage.
Yes, always. A legal ADU requires a permit, plans, and inspections here, and an unpermitted conversion can’t get a certificate of occupancy and creates problems at resale. We pull the permits and manage the inspections. Call (833) 716-6251 to talk through the plan set.
Often yes, if the bathroom and kitchenette can be planned around the existing water heater and slab. Moving plumbing is doable but adds cost and schedule. We assess this in stage one. Call (833) 716-6251 and we’ll walk the footprint with you.
Most projects land between $45,000 and $130,000, depending on garage size, condition, utility relocation, and finish grade. Call (833) 716-6251 for an exact quote; estimates are free.
Every conversion we build is covered by our 730-Day Done Right Promise: if it’s not done right, we make it right. That covers workmanship, and it’s backed in writing. Call (833) 716-6251 to see how it applies to your project.
Ready to price your conversion?
Call (833) 716-6251 to schedule a free on-site estimate for your Garage Conversion ADU in Sunny Isles Beach. We’ll walk the garage, check the utilities and slab, and give you a written line-item number with permits included. That’s part of our wider Home Additions & ADU work, and if you’re also resurfacing the driveway, see Asphalt Driveways & Resurfacing in Sunny Isles Beach. We cover the whole Sunny Isles Beach area, plus nearby North Miami Beach and Aventura. Calls are answered by a live person, 24/7.
Written by the team at Groundwork Construction Co.